Homeowner guide

ADU Permit Process in Los Angeles

By the Zen Homes team · Last reviewed November 26, 2026 · 7 min read

New two-story home framing in progress

State law and the City of Los Angeles ordinance treat a qualifying ADU as a ministerial approval: if the plans meet the rules, the city has to approve them, and it has a clock. This guide walks through the steps in order.

It covers the City of Los Angeles and is a summary, not legal advice. Properties outside the city follow a different local ordinance, though the state rules are the same.

At a glance

Step 1: Check eligibility and the type of ADU

Start by looking up your lot on ZIMAS. City Planning’s guidance (ZA Memo 143) says ADUs are permitted through a ministerial process in all areas zoned to allow single-family or multifamily residential use, where a dwelling is proposed or already exists on the lot (ZA Memo 143). Junior ADUs (up to 500 sq ft inside a single-family home) are allowed in zones that permit single-family use.

The memo separates two paths. State-law ADUs must be approved if they meet the state standards, and are not subject to local zoning or design standards. Ordinance ADUs follow the city’s own ADU ordinance, LAMC 12.22 A.33. One detached, newly built state-law ADU can be up to 800 sq ft with a height limit of 16 feet (18 feet near qualifying transit) and four-foot side and rear setbacks. Converting an existing garage or room generally needs no new setback.

Step 2: Prepare your plans and documents

A complete application typically includes a site plan, architectural plans, structural drawings and calculations, plumbing, electrical and mechanical plans, a Title 24 energy compliance report and CALGreen documentation. LADBS’s Information Bulletins list the exact documents by project type, so check the current ADU bulletins on the LADBS ADU page.

You may be able to save time and design cost with a pre-approved plan. The LADBS Standard Plan Program lists pre-approved plans, including a free city-owned plan for a one-story, one-bedroom ADU of about 455 sq ft (program details). LADBS still checks zoning and foundation conditions for your specific lot, and a pre-approved plan may not fit every site.

Step 3: Line up other city clearances

Before the permit is issued, other City departments may need to sign off. LADBS’s ADU bulletin P/BC 2026-150 lists approval from the Bureau of Engineering for sewer capacity and availability, and summaries of the bulletin note clearances from LADWP where a structure is in or within 10 feet of a utility easement, from LAFD for hydrants and access, and from City Planning (ADU sewer availability clearance in Los Angeles; MyCaliforniaADU: Los Angeles ADU Rules 2026). Which ones apply depends on the lot, so ask early. Clearances are a common source of delay.

Step 4: Submit through ePlanLA

Applications are submitted through the City’s ePlanLA (City of Los Angeles) online system. State law gives the agency 15 business days to determine whether the application is complete and to tell you in writing what is missing. Once the application is complete, the agency must approve or deny it within 60 days, and if it does not act in that time the application is deemed approved (HCD ADU Handbook; ZA Memo 143, Q.24). A denial must come with a full written list of what is deficient and how to fix it.

That 60-day clock starts only when your application is complete, and it does not include the time you spend on design or on construction afterward. Do not read it as the whole project timeline.

Step 5: Understand the fees

Plan check and permit fees are set by the City, and your LADBS estimate will show them. Under state law, no impact fee may be charged on an ADU of 750 sq ft or less. Larger ADUs pay impact fees in proportion to the size of the main home. For an ADU built inside an existing home, no new utility connection or connection fee may be required, but a new detached ADU can be. See the cost breakdown in our guide to how much an ADU costs in Los Angeles.

Rules homeowners ask about

Step 6: Build, inspect and close out

After the permit is issued, work is inspected in stages. When construction is finished, you request a final inspection and, where applicable, a Certificate of Occupancy. Keep the permit and building card (B-8) with your records. If you hire a contractor, verify the license on the CSLB site and ask them to confirm each inspection in writing.

Planning an ADU or garage conversion?

Zen Homes can handle the plans, permits and construction. Start with a free consultation.

Request a Free Quote Call 747-389-3783

Frequently asked questions

How long does it take to get an ADU permit in Los Angeles?

After a complete application is submitted, the city must approve or deny it within 60 days, or it is deemed approved. The city has 15 business days beforehand to tell you whether the application is complete. Design time before you apply and construction time after approval are separate.

Do I have to live on the property to build or rent an ADU?

No local owner-occupancy requirement can be imposed on an ADU under current state law. Local rules may require rentals to be longer than 30 days, so short-term rentals are limited.

Can I convert my garage into an ADU in Los Angeles?

Often yes. State-law ADUs created within an existing structure are not subject to the size limits and generally need no new setback. Replacement parking is not required when the garage is converted. Your lot, zoning overlays and the structure’s condition still matter.

Can I use a pre-approved ADU plan?

Yes. LADBS’s Standard Plan Program includes a free city-owned one-story, one-bedroom plan of about 455 sq ft and other pre-approved plans you can buy from their designers. LADBS still reviews the site-specific conditions for your lot.

What if I already have an unpermitted ADU?

State law (AB 2533) limits when a city can deny a permit for a qualifying unpermitted ADU or JADU built before January 1, 2020. LADBS has a separate bulletin, P/BC 2026-161, for that path. Ask LADBS or a licensed professional whether yours qualifies.

Sources

  1. LADBS: Accessory Dwelling Unit (ADU): ADU ordinance, bulletins P/BC 2026-150 and P/BC 2026-161, standard plans.
  2. LA City Planning ZA Memo 143, Rev. 1 (Aug. 1, 2025): ministerial approval, state-law and ordinance ADU standards, parking and the 60-day rule.
  3. California HCD ADU Handbook (March 2026): 15-business-day completeness review, 60-day approve or deny, denial comments, garage demolition, sprinklers, owner-occupancy and rental terms.
  4. Cal. Gov. Code §66311.5: impact fees and utility connections.
  5. LADBS: ADU Standard Plan Program: pre-approved plans, including city-owned plan YOU-ADU (455 sq ft).
  6. EMC Building Corp: ADU sewer availability clearance in Los Angeles (quotes LADBS bulletin P/BC 2026-150, §VI); MyCaliforniaADU: Los Angeles ADU Rules 2026 (summary of LADBS bulletin P/BC 2026-150): secondary summaries of the clearances listed in LADBS bulletin P/BC 2026-150.
  7. ePlanLA (City of Los Angeles): online plan check submission.
  8. Plan Checker Pro: LA ADU Permits guide: typical application document list (secondary source; confirm with LADBS bulletins).

This guide is general information, not legal, engineering or financial advice. Cost figures are typical estimates from the published sources above, not quotes, and are not Zen Homes prices. Codes, fees and city procedures change, so confirm current rules with the City of Los Angeles before you build.